BATHROOM REMODEL ESTIMATE — INTERNAL WORKSHEET Teaching example prepared October 15, 2026. Editable assumptions, not current market rates. Project / client / address: [enter project, client and address] Prepared by / estimate date / revision: [enter name, date and revision] Valid until: [confirm supplier validity and enter date] Protection and demolition labor: 20 hours × $45.00 = $900.00 Protect hall; remove existing shower finishes, floor tile, vanity and toilet. Loaded labor cost. Protection supplies and disposal: 1 lot × $300.00 = $300.00 Floor protection, containment supplies, hauling and disposal fees. Plumbing and vanity installation: 1 trade quote × $1,500.00 = $1,500.00 Existing locations retained; rough materials, drain connection, set vanity/top and connect listed fixtures. Fixture supply below. Electrical and ventilation: 1 trade quote × $850.00 = $850.00 Replace one fan using verified existing duct route; reconnect one existing light. Includes fan and labor; no panel work. Shower substrate and waterproofing materials: 1 assembly × $800.00 = $800.00 3 × 4 ft shower base/drain assembly, wall substrate and compatible waterproofing components; verify actual system. Shower substrate and waterproofing labor: 10 hours × $45.00 = $450.00 Preparation, assembly installation and required testing; confirm system instructions and inspection sequence. Wall tile selection allowance: 110 sq ft purchased × $5.00 = $550.00 100 sq ft installed + 10% illustrative waste. Supply only; round to actual boxes. Floor tile selection allowance: 66 sq ft purchased × $5.00 = $330.00 60 sq ft installed + 10% illustrative waste. Supply only; shower base is separate. Tile setting materials: 1 lot × $200.00 = $200.00 Mortar, grout, sealant and edge/transition profiles; verify coverage and layout. Tile installation labor: 36 hours × $45.00 = $1,620.00 100 sq ft walls and 60 sq ft floor; simple layout, no niche, bench or specialty pattern. Vanity and integrated top allowance: 1 set × $1,500.00 = $1,500.00 Stock 36-inch vanity with integrated top/sink; supply and delivery, installation in plumbing quote. Plumbing fixture allowance: 1 set × $700.00 = $700.00 Toilet, faucet and compatible shower valve/trim supply and delivery; installation in plumbing quote. Paint, trim and final cleanup labor: 10 hours × $45.00 = $450.00 Prepare and paint remaining walls/ceiling, replace up to 24 linear ft base trim, final clean and punch list. Paint and trim materials: 1 lot × $250.00 = $250.00 Primer, paint, trim and consumables for listed surfaces. Permit and job-specific fees: 1 provisional sum × $300.00 = $300.00 Placeholder only; contractor coordinates permits/inspections. Replace with local determination and actual fees. Direct-cost subtotal: $10,700.00 Internal risk reserve: $535.00 Cost base: $11,235.00 Markup (30%, covering overhead and profit): $3,370.50 SELLING PRICE BEFORE APPLICABLE TAX: $14,605.50 Purchase taxes / freight omitted from inputs: [verify and add to costs before finalizing] Customer tax treatment / amount / final total: [verify separately; not calculated here] Markup is not margin or net profit. Avoid duplicating overhead or subcontractor costs. SCOPE, ALLOWANCES, EXCLUSIONS AND SCHEDULE Fictional same-layout bathroom: 8 × 9 ft room footprint; 3 × 4 ft shower base; 60 sq ft of measured floor tile and 100 sq ft of shower wall tile. Verify site dimensions before use. Existing fixture locations, suitable framing/substrate and usable fan duct assumed. Contractor supplies listed products and coordinates trades, permits and inspections. Retain existing mirror, light, towel bars and shower curtain/rod. Allowances: wall tile $550; floor tile $330; vanity/top $1,500; fixture set $700, all direct-cost supply budgets. Tile freight is excluded pending a quote; vanity/fixture delivery is included. Installation is priced separately. Sample costs exclude taxes; verify purchase taxes, delivery and customer tax treatment before quoting. Exclusions: structural or concealed-damage repairs, hazardous-material testing/remediation, layout or service relocation, panel/duct upgrades, custom glass, niche/bench, specialty tile patterns and work outside this room. If a concealed condition appears, document it and agree scope, price and schedule before affected extra work. Internal risk reserve: $535 ($300 for extra preparation labor and $235 for incidental access/disposal costs). It is an internal budgeting allowance, not an automatically refundable client selection allowance. Replace with a project-specific risk assessment. Schedule assumption: 15 working days after selections, deliveries, permits and trade availability are confirmed, with drying, testing and inspection time verified for the actual assembly. This is a teaching assumption, not a promised duration. Before issue: confirm every model, supplier quote/date, tax treatment, selection deadline, payment milestone, valid-until date and local contract requirements. This worksheet is an internal estimate, not a ready-to-sign contract. Selection deadlines: [item / owner / decision date / order date] Payment milestones: [completed work / amount / due condition; verify local requirements] Source quotes: [supplier or trade / reference / quote date / expiry / inclusions] Review owner / date: [name / date] Source: https://www.greenlitbid.com/guides/how-to-estimate-a-bathroom-remodel